The Vasco Rd Safety Improvements Project - Phase 1 is designed to improve the safety of approximately 1 mile of Vasco Rd between the cities of Brentwood and Livermore. This stretch of twisting Vasco Rd has heavy, fast moving traffic and a history of serious injury accidents. The project consists of installing a concrete median barrier along the 1 mile project limits and widening the southbound pavement to provide a truck climbing lane, thereby eliminating the gap in the existing truck climbing lanes along Vasco Rd. To accommodate these safety improvements, 6 retaining walls, storm drains, wildlife crossings, and a bridge widening will be constructed. This project is anticipated to take 1.5 yrs (2 construction seasons) to complete, anticipated in December 2011. Check out this blog from time to time to see updates on construction progress and facts about the project.

Saturday, June 26, 2010

Inclinometers and Bridge Foundation Work Begins

This week Teichert Construction started to access the hillside north of Brushy Creek bridge to prepare for installation of 2 retaining wall structures. Part of this preparation work is exploratory drilling and inclinometer installation. Exploratory drilling in the hillside is necessary for County engineers to confirm the existing hillside soil conditions and make any necessary modifications to the retaining wall design prior to actual installation. Inclinometers are plastic casings (90 ft in depth) installed on the hillside that are located behind the retaining wall location that measure any hillside movement. Measuring any "hillside" creep is necessary as part of the overall installation process to ensure that retaining wall construction isn't affecting slope stability and as well as providing long term maintenance monitoring. Progress continues with the Brushy Creek bridge widening effort as Teichert Construction crews excavated for foundation footings at the south abutment. This operation will be followed with pile driving, anticipated to begin next week (6/28/10).



Looking north at an inclinometer location. Note, the portion of the hillside, leftside in the picture (down slope) will be excavated for the retaining wall itself.


.
Inclinometer casing.



Teichert Construction crew excavating the footing for the southern abutment.

Monday, June 21, 2010

EXPECT DELAYS: 6/24

Teichert Construction will be implementing 1 lane traffic control along Vasco Rd (at Brushy Creek bridge) on Thursday, 6/24/10, from 9 am to 3 pm. Commuters should expect delays while County biologists work on the bridge to re attach netting to prevent birds from nesting on the bridge structure itself. Surprisingly, the concrete angle points on bridges are prime habitat for birds to form "mud" nests. Birds that form new homes on the bridge may delay the project so County biologists monitor and implement measures to prevent birds from establishing nests. On Brushy Creek bridge, netting is installed under the bridge at the abutments and along the edge of deck. Due to the high winds, netting must be constantly maintained and reattached to prevent it from blowing onto the roadway itself or falling into the creek, which is sensitive habitat.

Netting installed under Brushy Creek bridge at the angle point created by the existing abutment and superstructure.

Saturday, June 19, 2010

Brushy Creek Bridge Demolition

Teichert Construction crews completed the majority of the Brushy Creek Bridge demolition this week. The demolition operations were limited to the existing barrier rail on the bridge along northbound Brushy Creek Bridge. A minimal portion of the existing deck was removed so the final concrete pour (closure pour) will transition the existing bridge deck to the new bridge grades. Portions of the exposed rebar on the existing bridge will connect to rebar/concrete in portions of the new bridge widening.

View of the existing bridge with the northbound barrier rail removed and exposed rebar.


County Construction Inspection reviews the operation to confirm the limits of demolition and ensure that the existing structure remains undamaged.

Wednesday, June 16, 2010

Getting Ready for Bridge Demolition

One of the Stage 1 construction improvements is the Brushy Creek Bridge widening. Dewatering of Brushy Creek was just the first step in preparing the area for the actual bridge construction. The next step is preparing access to the future bridge foundations, establishing a work area in the dewatered creek, and demolishing the existing bridge barrier rail. Teichert Construction began these initial operations earlier this week by adding metal plates over the creek to protect the bypass pipe from construction equipment and demolition debris. A breaker on the back of a backhoe will do most of the demolition work later this week.


A backhoe with a breaker stages on the work side of the k-rail.


Since the k-rail will prevent vehicles from entering the work area where the existing edge of bridge deck (barrier rail) will be demolished, it must be doweled into the existing bridge deck to prevent movement from collisions with vehicles that may have gone astray.


Looking down from the barrier rail (to be demolished), Teichert has established a work area for future falsework and pile driving operatons while protecting the dewatering pipe from construction equipment and demolition debris.

Friday, June 11, 2010

Stage 1 Traffic Handling Plan Complete

Teichert Construction completed implementation of the Stage 1 Traffic Handling Plan this week. This plan consists of removing existing rumble strips, traffic striping, and installing temporary concrete barriers (k-rail) along the roadway to establish a safe work zone away from vehicle traffic. A significant portion of this work took place at the northern project limit to accommodate the future Brushy Creek Bridge widening work and Soil Nail wall operations.



Looking Northbound along Vasco Rd at the northern project area.


The established work area behind the k-rail for the Brushy Creek Bridge widening work.

Thursday, June 10, 2010

Water Control of Brushy Creek

Teichert Construction began implementing their water control plan in the Brushy Creek Bridge widening area. Water control or dewatering of Brushy Creek consists of establishing a "dry" work zone in the creek in advance of actual bridge widening construction. The water control plan (also referred to as dewatering plan) consists of installing a silt filter barrier at the downstream work limits and upstream cofferdams. The existing creek flow is diverted through a plastic pipe so clean upstream water bypasses the work area and is discharged downstream of the work area. The silt filter barrier at the downstream end ensures that any work zone runoff is treated prior to flowing downstream of the work area. Initial water quality sampling that compares upstream and downstream water quality during this dewatering operation indicates that none of the operations have adversely impacted the creek water quality. County Construction Inspection provide biological monitoring to identify and manage wildlife encountered during creek work since California red-legged frogs have been sighted this last week.

While creating access to the creek, an excavator makes repairs to the ESA-silt Fence. Maintaining the fence along the project limits is vital in preventing animals from entering the work zone and being harmed as well as treating storm water runoff that may enter the creek.


Looking downstream (from the upstream cofferdam area), Teichert Construction begins to secure the dewatering bypass pipe with existing river rock.

Saturday, June 5, 2010

EXPECT DELAYS: 6/7 to 6/9

Teichert Construction will be doing roadwork along Vasco Rd on Monday, 6/7, to Wednesday, 6/9. Advance notice was given to commuters this past Friday, 6/4, by portable changeable message boards that are along the Vasco Rd. The anticipated construction work hours in the roadways are from 8:30 am to 3:00 pm. The purpose of this work (anticipated to take 3 days) is to continue the installation the Stage 1 traffic control. Teichert Construction removed the existing rumble strips and striping this past Friday (6/7). Construction operations in the road this upcoming week will be focused on installing the k rail (temporary concrete barriers) for Stage 1 traffic control. Upon completion this stage's traffic control, the majority of construction activity can take place behind the temporary k-rail, 2 lanes Vasco Rd traffic will be routed through the work zone, and construction impacts to Vasco Rd commuters will be minimized.

Miles of Fencing!

Since the Vasco Road Safety Improvements Project-Phase 1 project limits are within a sensitive animal migration corridor, the project has detailed fencing requirements to protect wildlife and ensure their safe access from one side of the road to the other. Installation of 5 miles of temporary wildlife exclusion fencing around the work perimeter is the first order of work to prevent animals from entering the job site. No significant road work, grading, or accessing of Brushy Creek (for the bridge widening work) can occur until all the temporary wildlife exclusion fence is installed. Some of the animals that the fence is designed to protect are the San Joaquin Kit Fox and California Tiger Salamander. The 24" high, black plastic mesh fence also protects construction workers from snakes that may enter work area overnight and hider under stockpiled materials. Construction workers have encountered (almost on a daily basis) rattlesnakes (along with gopher and king snakes) while installing this fence.


Temporary wildlife exclusion fencing along hillside north of Brushy Creek bridge.


Temporary wildlife exclusion fencing at the staging area.