The Vasco Rd Safety Improvements Project - Phase 1 is designed to improve the safety of approximately 1 mile of Vasco Rd between the cities of Brentwood and Livermore. This stretch of twisting Vasco Rd has heavy, fast moving traffic and a history of serious injury accidents. The project consists of installing a concrete median barrier along the 1 mile project limits and widening the southbound pavement to provide a truck climbing lane, thereby eliminating the gap in the existing truck climbing lanes along Vasco Rd. To accommodate these safety improvements, 6 retaining walls, storm drains, wildlife crossings, and a bridge widening will be constructed. This project is anticipated to take 1.5 yrs (2 construction seasons) to complete, anticipated in December 2011. Check out this blog from time to time to see updates on construction progress and facts about the project.

Saturday, October 2, 2010

Soil Nail Wall 7 Operations

After excavating for the first lift of soil nails for Wall 7, Teichert Construction began the process of installing soil nails, steel reinforcement, and shotcrete to form the structural wall itself. This sequencing of work typically takes at least a week from start to finish (excavation, drilling, nail installation and grouting, steel reinforcement, and then shotcrete). County Inspection staff perform onsite inspection of the complete operation to ensure that the proper design specifications are achieved. Inspectors are responsible to verify that the contractor excavates the hillside to the surveyed limits, confirm that soil nails are installed and grouted to the designed lengths, and ensure that the proper reinforcing steel is placed and shotcrete is applied properly.

After excavation, soil nails (40 to 50 ft in length) are installed.

Geocomposite drains ("black strips") are evenly spaced along the cut face.


Prior to shotcrete facing, reinforcing steel mesh and rebar are installed.

An initial layer of shotcrete is applied to the prepared wall face.

Shotcrete is uniformed applied until the design thickness is achieved.